Milestones
- Tier: Free, Premium, Ultimate
- Offering: GitLab.com, GitLab Self-Managed, GitLab Dedicated
Milestones help track and organize work in GitLab. Milestones:
- Group related issues and merge requests to track progress toward a goal.
- Support time-based planning with optional start and due dates.
- Work alongside iterations to track concurrent timeboxes.
- Track releases and generate release evidence.
- Apply to projects and groups.
Milestones can belong to a project or group. Project milestones apply to issues and merge requests in that project only. Group milestones apply to any issue or merge request in that group's projects.
For information about project and group milestones API, see:
Milestones as releases
Milestones can be used to track releases. To do so:
- Set the milestone due date to represent the release date of your release. If you do not have a defined start date for your release cycle, you can leave the milestone start date blank.
- Set the milestone title to the version of your release, such as
Version 9.4
. - Add issues to your release by selecting the milestone from the issue's right sidebar.
Additionally, to automatically generate release evidence when you create your release, integrate milestones with the Releases feature.
Project milestones and group milestones
A milestone can belong to project or group.
You can assign project milestones to issues or merge requests in that project only. You can assign group milestones to any issue or merge request of any project in that group.
For information about project and group milestones API, see:
View project or group milestones
To view the milestone list:
- On the left sidebar, select Search or go to and find your project or group.
- Select Plan > Milestones.
In a project, GitLab displays milestones that belong to the project. In a group, GitLab displays milestones that belong to the group and all projects and subgroups in the group.
View milestones in a project with issues turned off
If a project has issue tracking turned off, to get to the milestones page, enter its URL.
To do so:
- Go to your project.
- Add:
/-/milestones
to your project URL. For examplehttps://gitlab.com/gitlab-org/sample-data-templates/sample-gitlab-project/-/milestones
.
Alternatively, this project's issues are visible in the group's milestone page.
Improving this experience is tracked in issue 339009.
View all milestones
You can view all the milestones you have access to in the entire GitLab namespace. You might not see some milestones because they're in projects or groups you're not a member of.
To do so:
- On the left sidebar, select Search or go to.
- Select Your work.
- On the left sidebar, select Milestones.
View milestone details
To view more information about a milestone, in the Milestones page, select the title of the milestone you want to view.
The milestone view shows the title and description. The tabs below the title and description show the following:
-
Issues: Shows all issues assigned to the milestone. Issues are displayed in three columns named:
- Unstarted Issues (open and unassigned)
- Ongoing Issues (open and assigned)
- Completed Issues (closed)
-
Merge Requests: Shows all merge requests assigned to the milestone. Merge requests are displayed in four columns named:
- Work in progress (open and unassigned)
- Waiting for merge (open and assigned)
- Rejected (closed)
- Merged
- Participants: Shows all assignees of issues assigned to the milestone.
- Labels: Shows all labels that are used in issues assigned to the milestone.
Burndown charts
The milestone view contains a burndown and burnup chart, showing the progress of completing a milestone.
Milestone sidebar
The sidebar on the milestone view shows the following:
- Percentage complete, which is calculated as number of closed issues divided by total number of issues.
- The start date and due date.
- The total time spent on all issues and merge requests assigned to the milestone.
- The total issue weight of all issues assigned to the milestone.
- The count of total, open, closed, and merged merge requests.
- Links to associated releases.
- The milestone's reference you can copy to your clipboard.
Create a milestone
Version history
- Changed the minimum user role from Developer to Reporter in GitLab 15.0.
- Changed the minimum user role from Reporter to Planner in GitLab 17.7.
You can create a milestone either in a project or a group.
Prerequisites:
- You must have at least the Planner role for the project or group the milestone belongs to.
To create a milestone:
- On the left sidebar, select Search or go to and find your project or group.
- Select Plan > Milestones.
- Select New milestone.
- Enter the title.
- Optional. Enter description, start date, and due date.
- Select New milestone.
Edit a milestone
Version history
- Changed the minimum user role from Developer to Reporter in GitLab 15.0.
- Changed the minimum user role from Reporter to Planner in GitLab 17.7.
Prerequisites:
- You must have at least the Planner role for the project or group the milestone belongs to.
To edit a milestone:
- On the left sidebar, select Search or go to and find your project or group.
- Select Plan > Milestones.
- Select a milestone's title.
- In the upper-right corner, select Milestone actions ({ellipsis_v}) and then select Edit.
- Edit the title, start date, due date, or description.
- Select Save changes.
Close a milestone
Version history
- Changed the minimum user role from Reporter to Planner in GitLab 17.7.
A milestone closes after its due date. You can also close a milestone manually.
When a milestone is closed, its open issues remain open.
Prerequisites:
- You must have at least the Planner role for the project or group the milestone belongs to.
To close a milestone:
- On the left sidebar, select Search or go to and find your project or group.
- Select Plan > Milestones.
- Either:
- Next to the milestone you want to close, select Milestone actions ({ellipsis_v}) > Close.
- Select the milestone title, and then select Close.
Delete a milestone
Version history
- Changed the minimum user role from Developer to Reporter in GitLab 15.0.
- Changed the minimum user role from Reporter to Planner in GitLab 17.7.
Prerequisites:
- You must have at least the Planner role for the project or group the milestone belongs to.
To delete a milestone:
- On the left sidebar, select Search or go to and find your project or group.
- Select Plan > Milestones.
- Either:
- Next to the milestone you want to delete, select Milestone actions ({ellipsis_v}) > Delete.
- Select the milestone title, and then select Milestone actions ({ellipsis_v}) > Delete.
- Select Delete milestone.
Promote a project milestone to a group milestone
Version history
- Changed the minimum user role from Reporter to Planner in GitLab 17.7.
If you are expanding the number of projects in a group, you might want to share the same milestones among this group's projects. You can promote project milestones to the parent group to make them available to other projects in the same group.
Promoting a milestone merges all project milestones across all projects in this group with the same name into a single group milestone. All issues and merge requests that were previously assigned to one of these project milestones become assigned to the new group milestone.
This action cannot be reversed and the changes are permanent.
Prerequisites:
- You must have at least the Planner role for the group.
To promote a project milestone:
- On the left sidebar, select Search or go to and find your project.
- Select Plan > Milestones.
- Either:
- Next to the milestone you want to promote, select Milestone actions ({ellipsis_v}) > Promote.
- Select the milestone title, and then select Milestone actions ({ellipsis_v}) > Promote.
- Select Promote Milestone.
Assign a milestone to an issue or merge request
Every issue and merge request can be assigned one milestone. The milestones are visible on every issue and merge request page, on the right sidebar. They are also visible in the issue board.
To assign or unassign a milestone:
- View an issue or a merge request.
- On the right sidebar, next to Milestones, select Edit.
- In the Assign milestone list, search for a milestone by typing its name. You can select from both project and group milestones.
- Select the milestone you want to assign.
To assign or unassign a milestone, you can also:
- Use the
/milestone
quick action in a comment or description - Drag an issue to a milestone list in a board
- Bulk edit issues from the issues list
Filter issues and merge requests by milestone
Filters in list pages
You can filter by both group and project milestones from the project and group issue/merge request list pages.
Filters in issue boards
From project issue boards, you can filter by both group milestones and project milestones in:
From group issue boards, you can filter by only group milestones in:
Special milestone filters
Version history
- Logic for Started and Upcoming filters changed in GitLab 18.0.
When filtering by milestone, in addition to choosing a specific project milestone or group milestone, you can choose a special milestone filter.
- None: Show issues or merge requests with no assigned milestone.
- Any: Show issues or merge requests with an assigned milestone.
- Upcoming: Show issues or merge requests with an open assigned milestone starting in the future.
- Started: Show issues or merge requests with an open assigned milestone that overlaps with the current date. The list excludes milestones without a defined start and due date.